The work
Precast plank decks are common in modern multi-storey construction, and they need a screed that bonds well, levels fast and reaches every part of the deck.
Our placing booms let us deliver screed across upper floors without craning plant up, and self-compacting systems remove the need for late power floating. Between them, an upper deck stops being a special case and becomes a normal day's work.
That is the honest summary of this page. The screed itself is not the hard part. Getting it up there, across a deck that has camber and joints and a tight programme, on a building that may still be going up around you, is the hard part. That is what we are set up for.
Four things separate this from screeding a ground floor.
Bonded, unbonded or floating? On a precast deck all three are used, and each has a different minimum depth and a different consequence for the deck survey. Floating over insulation is normal where underfloor heating or acoustic separation is required.
Which system, flowing or self-compacting? Flowing screed covers fast and levels itself. Self-compacting also removes the late power floating step, which on an upper deck means no plant and no crew returning to that floor in the evening. Site hours usually decide it. See flowing screed and self-compacting screed.
Which binder? Calcium sulphate flows well and is widely used but is moisture-sensitive and normally needs its laitance removing before adhered coverings. Cementitious avoids both and costs more. The finishes schedule should decide.
Has the deck been surveyed? This is the item that causes most of the arguments. Camber, level and any out-of-tolerance planks change the volume, and volume changes the price and the load. Survey first.
Is acoustic performance specified? Separating floors in residential and hotel work often carry acoustic requirements, which drive the build-up, the isolation layer and the perimeter detail.
We survey the deck, confirm datums and falls, and plan the pour and boom positions around the building and the programme. The survey tells us the real depth range and therefore the real volume, which is what the price should be built on.
Plank joints are checked and the perimeter detail agreed before anything is pumped. Where insulation or an isolation layer is specified, we confirm it is laid, continuous and properly taped at the perimeter.
Screed is pumped and placed to level, with the system chosen to suit the finish, the loading and the time available. Dapple bars work the material to help it level and release air. With self-compacting systems that is the end of it, with no return visit to power float.
Levels are checked as we go rather than at the end, because a deck at height is not a place to discover a problem after the material has gone off.
We run two track-mounted placing booms, which are two of only three in the country, plus our own concrete line pumps. All operated by our own people.
Boom reach is what lets us screed upper decks without craning plant onto the floor. That saves crane time, saves a lift plan, saves the deck loading that comes with parking plant on it, and removes a dependency on somebody else's programme. On a constrained city site with one crane and a queue for it, that dependency is often the thing that delays the screed.
Where a boom is not the right answer, our line pumps are. Placing is planned as part of the works from the start, with pump positions, hose runs, outrigger loadings and wash-out agreed before we mobilise. See concrete pumping.
Screed surface regularity is normally specified to BS 8204, measured as the maximum deviation under a 2m straightedge:
| Class | Maximum deviation | Typically used for |
|---|---|---|
| SR1 | 3mm | High specification floors and demanding floor finishes |
| SR2 | 5mm | The general default for most commercial projects |
| SR3 | 10mm | Utility areas and floors taking a thick applied finish |
SR2 is the usual default. Screed materials are classified by binder type under BS EN 13813.
On a precast deck the achievable class depends on the deck as much as the screed, which is why the survey comes first. A screed laid on a deck outside tolerance will either use more material or fail to hit the class, and both outcomes are better priced than discovered.
We survey the finished screed against the class specified and issue the results.
Pumped screed covers a deck quickly. What governs the day is access: how many boom or pump set-ups the building allows, how the material gets to the pump, and how much of the deck is genuinely ready.
We programme from the ready date backwards. On multi-storey work that usually means fitting into a floor-by-floor cycle, and we will tell you at tender whether the cycle you have is realistic for the screed.
Constructionline Gold registered. Avetta and SSIP accredited. Member of the Nuclear Industry Association.
FAQs
Send us the drawings and the specification, and we'll tell you straight whether we can deliver it, and how.
Discuss your project