TR34 FM1, FM2, FM3, FM4: Which Flatness Class Do You Need?

TR34 flatness classes FM1 to FM4 set how flat and level a free movement industrial floor must be, with FM1 the tightest and FM4 the most relaxed. The racking height and the trucks decide which class a floor needs, and specifying a tighter class than the operation uses adds cost for no benefit.

TR34 is the Concrete Society's Technical Report 34, now in its 4th edition, and it is the reference for concrete industrial ground floors in the UK. This guide explains what the classes measure, how to choose one and how the finished floor is checked.

What TR34 measures

TR34 controls two properties separately, because a floor can be level overall and still be bumpy underfoot, or smooth and still out of level:

  • Property E (levelness) is the difference in height between points 3m apart on a grid across the floor. It controls the gradual rise and fall that tilts a mast at height.
  • Property F (flatness) is the change in the difference in height between two consecutive measurements, each over 300mm. It controls the short-wavelength bumps that make a truck rock.

Compliance is assessed on the 95th percentile value of the readings, not on the single worst reading, so a floor isn't failed by one bad spot.

The free movement classes

Free movement floors are those where trucks can travel anywhere, which covers most warehouses, distribution centres and factories. The limits are:

ClassProperty E (levelness)Property F (flatness)Typically specified for
FM14.5mm1.8mmReach trucks above 13m without side-shift
FM26.5mm2.0mmReach trucks 8m to 13m without side-shift
FM38.0mm2.2mmReach trucks up to 8m, or 13m with side-shift
FM410.0mm2.4mmWorkshops with lift heights up to 4m, retail with applied screeds

How to choose the class

The class is a function of the materials handling equipment, not of the building. Two questions settle most of it:

  • How high will the trucks lift? The higher the lift, the further a small tilt at floor level moves the load at the top of the mast.
  • Do the trucks have side-shift? Side-shift lets the driver correct the load position, so the same lift height can work on a more relaxed class.

Get the racking layout and the truck specification settled before the floor is priced. A floor specified for 8m trucks and later asked to serve 14m trucks is a problem that can't be put right without grinding or replacing the floor.

FM2 vs FM3: the common decision

For most modern warehouses the choice is between FM2 and FM3. FM2 suits reach trucks working between 8m and 13m without side-shift. FM3 suits lower lift heights, or 13m where the trucks have side-shift. If the racking is not yet designed, specify for the realistic future use rather than the tightest class available.

FM1 is for very high lifts without side-shift and is unusual. FM4 is for workshops, light industrial units and floors that will take an applied screed or finish.

Why over-specifying costs money

Each tighter class takes more care in placing, more passes in finishing and sometimes narrower pours, and a tighter tolerance carries more risk of remedial grinding after the survey. If the operation will never use the tolerance, that cost buys nothing. A flooring contractor who prices to the class should tell you at tender if the class looks tighter than the use needs.

Defined movement floors

Where trucks run on fixed paths in very narrow aisles, a defined movement specification applies instead. The tolerance is then measured along and across the defined aisles rather than on a grid across the whole floor, and the classes and survey method are different. The specification will say which applies, and confusing the two at tender is an expensive mistake.

How a floor is checked

The finished floor is surveyed against the specified class, normally by an independent specialist, and the results are issued at handover. A useful specification states who carries out the survey, when it happens, and what happens if readings fall outside the limits. Surveying before racking goes in matters, because remedial work is far harder once it is installed.

Flatness is mostly set by how the concrete is placed and levelled, before the finishing starts. On large floors a laser screed is the normal route to a consistent class across the whole floor plate. The power float finish then produces the hard-wearing surface.

Screeds use a different standard

TR34 covers concrete floors. Surface regularity for screeds is specified to BS 8204 as SR1, SR2 or SR3, which is 3mm, 5mm or 10mm maximum deviation under a 2m straightedge. See commercial floor screeds.

TR34 floors from Trent

Trent Construction Services lays power floated and laser screeded concrete floors for main contractors across the UK, to the TR34 class the specification names. FM2 is typical on our laser screeded floors, and smaller floors laid by hand in large bays typically reach FM3 or FM4. The finished floor is surveyed by an independent specialist, usually arranged and paid for by us. We work on commercial projects only.

See power floated concrete floors for the detail, or send us the drawings and the racking layout. Discuss your project.