A floor screed can typically take light foot traffic the next day and full loading after 7 to 28 days, depending on the screed. Floor coverings can only go down once the screed passes its moisture test, and that usually takes far longer than either.
That last milestone is the one that moves programmes. This guide explains the three stages, why the moisture test decides the covering date, what changes drying time, and how to plan for it.
The three milestones
| Milestone | Typically | What decides it |
|---|---|---|
| Light foot traffic | The next day | The screed system and the conditions |
| Full loading | 7 to 28 days | The screed system and its strength gain |
| Floor coverings | When the screed passes its moisture test | Depth, binder, conditions and the covering's moisture limit |
The first two are about strength. The third is about moisture, and it is the one to plan around.
Why the moisture test decides the covering date
Vinyl, rubber, resin, timber and most flooring adhesives are moisture-sensitive. Laid on a screed that is still too wet, they can blister, lift, debond or grow mould. So the covering manufacturer sets a maximum moisture level for the base, and the screed has to be tested against it before the floor layer starts.
The test is usually a relative humidity reading, taken with a hygrometer sealed to the surface of the screed. The limit to test against comes from the covering manufacturer and the relevant British Standard, so check the finishes schedule early. Different coverings in the same building can have different limits.
Rules of thumb that give a drying time per millimetre of depth are widely quoted, but they are unreliable. Drying varies too much with conditions to plan on one. The test decides.
What changes drying time
- Depth. Thicker screeds take disproportionately longer, because moisture has further to travel out. Flowing screeds are typically around 40 to 100mm deep.
- The binder. Calcium sulphate and cementitious screeds dry differently and are often tested differently. See cementitious vs calcium sulphate flowing screed.
- A weathertight building. Until the roof, windows and doors are in, the screed is drying against the weather.
- Temperature, humidity and air movement. Warm, dry, moving air takes moisture away. Cold, still, damp air does not.
- Other wet trades. Wet plastering and other wet work in the same space put moisture back into the air.
- Underfloor heating. Commissioning the heating to the manufacturer's heat-up profile helps, but only on that profile. Heating the screed hard and early can crack or debond it.
Can drying be speeded up?
Yes, within limits. The reliable levers are getting the building weathertight early, keeping it heated and ventilated, managing humidity, and running the underfloor heating to its profile. Choosing the screed system and the depth with the covering date in mind helps too.
Force-drying a screed hard against a fixed date carries risk, because a surface that tests dry can still hold moisture lower down. We don't promise rapid or forced drying. We'd rather agree a realistic drying period at tender.
Planning it into the programme
- Programme backwards from the covering date, not forwards from the screed date.
- Put the moisture test in the programme as an activity with an owner, not an assumption.
- Agree the covering's moisture limit at tender, from the finishes schedule.
- Sequence the wet trades so they aren't adding moisture to a space that should be drying.
On education projects, drying is usually what decides whether a summer holiday window works. See floor screeds for schools. In hospitals the same planning applies around ward handovers. See hospital floor screeds.
Screeds from Trent
Trent Construction Services installs flowing, self-compacting and traditional screeds for main contractors on commercial projects across the UK, with our own operatives and pumps. We plan drying into the programme from the start, and we take moisture readings before floor coverings where we are asked to. We work on commercial projects only.